HI-TECH crews working along side Access Limited Construction have began the installation of over 200,000 sf of anchored mesh at 5 different sites along the highway.

The HI-TECH crew with their specialized skills first began by removing all the loose rock, trees and brush on the slope to allow for Access Limited to begin drilling of the rock anchors. The rock scaling was done without incident or interruption of the traveling public. Once the rock scaling was complete the drilling of the anchors began. The anchors are 10’ deep on a 10 X 10 grid pattern. At site 6 installation of the cable nets on the slope has begun and we expect to move to site 5 in a few weeks.